Verabar V550 (Flanged Spring-Lock)
INSTALLATION INSTRUCTIONS
1.0 SCOPE
These instructions provide procedures for installing the
V550 Verabar flow sensor. Procedures are given for all
industrial flow measurement applications including
liquid, steam and gas service for both horizontal and
vertical piping configurations.
2.0 RECEIVING INSPECTION
The following tasks should be performed as part of the
receiving inspection procedure:
Check items received against the packing list.
Check sensor nameplate for proper model num-
ber, serial number and customer number.
Verify that the actual pipe diameter matches the
ID stated on the sensor nameplate.
Check the bullet shaped sensor tube for any
signs of damage. Damage to the sensor tube
may result in erroneous flow readings.
Check the round cover tube for any damage,
especially axial gouges or scratches. Damage to
the cover tube may prevent the ferrule from
sealing properly.
3.0 SAFETY PRECAUTIONS
The following tasks should be conducted prior to install-
ing the Verabar flow sensor:
Check maximum operating conditions on the flow
sensor nameplate and verify that they exceed the
maximum conditions of the installation. If any
pressure, temperature or flow limits will be
exceeded, consult the factory before proceeding.
Check that the pipe is depressurized and drained
prior to installation.
The Flanged Spring-Lock Model V550 is
designed for carbon and stainless steel pipes
with a schedule 10 or heavier wall thickness.
The V550 should not be used with PVC, copper,
aluminum, cast iron or thin-walled pipes or ducts.
If there is any question as to the proper
application for a model V550, consult the factory.
4.0 INSTALLATION PREPARATIONS
4.1 Location
For the most accurate flow measurement, a minimum
straight run of pipe is required. Table 1 shows the
minimum straight run requirements.
If longer straight runs are available, position the
Verabar such that the ratio of upstream straight run to
downstream straight run is approximately 4 to 1. If
straight run lengths are less than the values stated in
Table 1, consult the factory for additional accuracy and
location information.
Position straightening vanes such that the end closest
to the Verabar is half way between the Verabar and the
closest upstream configuration. For elbow installations,
mount the Verabar in the same plane as the closest
upstream elbow.
4.2 Orientation
Verify the proper sensor orientation by checking for an
“-H” (horizontal piping) or a “-V” (vertical piping) in the
model number on the Verabar nameplate.
Piping Configuration
Table 1. Straight Run Requirements
Vue de la page 0
1 2 3 4

Résumé du contenu

Page 1 - INSTALLATION INSTRUCTIONS

Verabar V550 (Flanged Spring-Lock) INSTALLATION INSTRUCTIONS 1.0 SCOPE These instructions provide procedures for installing the V550 Verabar flow

Page 2

4.2.1 Horizontal Piping For air or gas installations, mount the Verabar in the upper 160° of the pipe to allow any condensate to drain into the pipe (

Page 3 - 5.3 Insert Sensor

Figure 2. Verabar Model V550 Figure 3. Spring-Lock Cutaway • Using the appropriate weld gap (1/16” [1.5mm] typical), tack weld the mounting flange

Page 4 - Periodic Maintenance

Figure 7. Orientation of Flow Arrow 5.4 Insert Instrument Valves or Manifold 5.4.1 Valves If the Verabar does not have a valve head, install instrum